Project Services > Civils > St Johns Wood St. Johns Wood Substation for ABB Contract 1 - construction of a Gas Insulated Switchgear (GIS) building sub-structure (excluding excavation and demolition), approximately 5m below surrounding ground level. The structure consisted of a reinforced concrete foundation raft slab, with supporting columns and walls. All works were in-situ. Value: £1.2 million. Contract 2 - construction of the GIS building super-structure, involving structural steel support frames with composite cladding panels. Over half of the external cladding consisted of high-specification brickwork with a variety of architectural features. Internally, two-storey office facilities were constructed, including services installation and decoration. Value: £1.8 million. Contract 3 - enabling works undertaken within a live National Grid Transco site environment, including services. Value: £300,000.
Procurement Route: Traditional
Sector: Power
Value: £3.3 million
|
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||