The Site is located on the M11 northbound and southbound carriageways between J8 and J9, with a total site length of approximately 4.0km.
The scheme comprised the following:
-
Construction of 2 No crossovers for contra-flow works.
-
Crack & Seat repairs to existing concrete carriageway.
-
The installation of slip-formed concrete barrier system in the central reservation.
-
165mm overlay resurfacing and associated new white-lining/ stud installation.
-
Installation of trapezoidal drainage channel in C/R.
-
Gully connections in C/R.
-
Drainage repairs in verges.
-
Replace existing safety fencing in verges.
-
250m approx. carriageway FDR.
-
3 No emergency crossings points in the C/R throughout the scheme length.
All part of the Highways Agency’s South East Framework for Highways in Area 8.
Procurement Route: Framework Agreement
Sector: Highways Major Maintenance
Value: £5million